A deep dive into how maintenance organizations improved their planning and scheduling processes to save time and money.
Sedgman
PM Advanced provided both a printing tool and a visual way for Sedgman’s users to schedule work orders in a Gantt chart format. The planning is more thorough and detailed, which improved the quality of the maintenance process. Training initiatives such as one-on-two sessions allowed users to understand more about how to use both SAP and Prometheus solutions to help them more efficiently use their time and provide a better output.
Each of Sedgman’s Australian sites has a shutdown every three weeks, with a twelve-hour window to complete all work. During the shutdown planning process, SAP revisions are used, and the Prometheus solution helps the company better manage this process, which includes the ability for users to clearly see the status of all shutdown purchase orders. By having a clear understanding of the schedule in SAP, work management has improved considerably.
Hemlock Semiconductor
Hemlock Semiconductor purchased PM Advanced to consolidate its plant maintenance systems and processes. Upon implementation, Hemlock integrated its HR and PM modules for all maintenance planning and scheduling. By consolidating all maintenance processes into one platform, they were able to dramatically improve process efficiency and reduce operational costs. In addition, the software solution has enabled Hemlock to respond rapidly to breaks in maintenance work and allowed for an unparalleled 20 hours of preventive maintenance to be scheduled.
Optimizing Resource Planning with Real-Time SAP
- Runtime
- 40:55
- View count
- 238
Hemlock Semiconductor saved thousands of dollars by increasing plant maintenance efficiency and reducing its daily maintenance scheduling burden. By simplifying their complex SAP system, the company vastly improved efficiency and achieved its goal of 80% capacity planning, allocating an unprecedented 20% of its resources to immediate and disruptive work.
This was ground-breaking as little to no preventive maintenance was scheduled previously. And, by maintaining all data within SAP, Hemlock is now able to trust the information in SAP and eliminate the “silo effect” that once existed in the Plant Maintenance module. SAP users across the organization who are outside of the PM module can now track work orders, and executives can analyze and forecast costs; all from within SAP.
Century Aluminum
Within six months, Century Aluminum implemented Prometheus PM Advanced to consolidate its Plant Maintenance system and processes through all five facilities. 240 hours a year were saved annually due to custom KPIs. And, Century’s planners were able to save more than hours per week thanks to a simplified user interface and ensured data integrity. The custom KPIs allowed planners and schedulers to get the most out of data pertaining to: total hours reported, breakdowns, unplanned hours, planned hours, schedule compliance, plant maintenance compliance, and plant maintenance hours.
The semi-automated Graphical Work Order Scheduler (GWOS), which functions completely within SAP, provided Century Aluminum with a variety of options for organizing and assigning tasks quickly and accurately while displaying a Gantt chart that automatically refreshes with real-time updates. Furthermore, the auto-leveling functionality ensured workload capacity compliance and the mass change function allowed planners and schedulers to change user or system status on multiple work orders in one smooth, simple transaction.
The tool also allowed users to print all work orders and attach related documents in one compact step, thus saving countless hours and providing the option of printing multiple attachments at the same time. And, one-day training enabled users to feel comfortable with Prometheus PM Advanced. Training began with initial contact and continued beyond the implementation process to ensure an understanding of the solution and how it fits their business process.
OneSteel Steel and Recycling
While printing capability was a main driver for the Prometheus solution justification, OneSteel soon realized the value of having Prometheus tools such as the Navigator. One user said, “Navigator has been a huge success story for us. It really helps beginner SAP users or those who aren’t using SAP daily.” They set up the Navigator to reflect the actual process flow within the plant, ensuring stable processes and consistent results across all users. And, OneSteel made it even more intuitive by naming the buttons with a local descriptor such as “your orders”. Users were also enthusiastic about Mass Change, citing they saved 20 minutes per work order versus having to change each work order individually.
Navigate SAP With Ease - Demo
- Runtime
- 3:27
- View count
- 692
Overall, user acceptance of the Prometheus solutions was very positive. The company considered the Prometheus deployment a success based on how easily users embraced the tools and how the enhanced usability made planning and scheduling quicker. The company saw the planners’ adoption of SAP rise, as well as utilization of best practices improve. For example, OneSteel moved from the work order level to the operations level, creating more collaboration and visibility across the teams. OneSteel was able to achieve its goal of improving consistency among all teams. One user described the Prometheus solutions as “an enabler to get everyone to follow one process.”
“In creating the business case for a new solution, the productivity improvements of SAP PM, when combined with the Prometheus suite of tools, were estimated at over $3.0M annually – for just one site.” How much can your company save? Check out our business case calculator.
Global Paper Production Company
Since the initial deployment of Prometheus solutions at this global paper company, user adoption has spread through several sites around the globe. The most popular tool among users is the Material Shopping Cart because its search functionality was significantly faster than what they were experiencing in standard SAP.
Material and Service Shopping Carts - Demo
- Runtime
- 3:17
- View count
- 254
Print Manager and Material Shopping Cart have been deployed to nearly 150 sites, with 17 more deployments scheduled to occur by the end of 2013. GWOS and Mass Change have been deployed to 20 sites, with seven more deployments scheduled in 2013. To meet the needs of the company’s global work force, the solutions have been translated into five languages. The company has also reduced IT headaches by decreasing the number of systems the company is using for scheduling.![Effective-Maint-Productivity-=-Minimized-Equip-Downtime]()
Also, by having real-time tools to manage dates and scheduling commitments, the company has seen significant improvements in data quality. Sites are now more aligned because of the consistency brought by using the same planning and scheduling tools, which allows them to manage backlog consistently and produce quality metrics. Maintenance is now able to clearly see how their work impacts other areas because of better business intelligence metrics.
Summary
The enhanced functionality provided by Prometheus solutions is helping users across industries and regions to be more efficient and focus on planning and scheduling best practices. This helps reduce reactive work, which can easily cost three to five times as much as planned work.
Beginning planners benefit because the tools are more intuitive and easier to use than standard SAP. This helps with both training and end user adoption. Advanced users also find value in the solutions because they can better utilize SAP to manage dates and backlogs.